What is the primary goal of implementing an effective disaster recovery plan in a data center?

Ace the BICSI Data Center Design Consultant (DCDC) Certification. Enhance your skills with flashcards and multiple choice questions with detailed explanations. Prepare to excel!

The primary goal of implementing an effective disaster recovery plan in a data center is to protect data and ensure uptime. This involves creating strategies and processes that enable the rapid restoration of IT systems and data following a disruptive event, such as hardware failure, natural disasters, cyberattacks, or power outages.

Disaster recovery focuses on minimizing downtime and data loss, which are critical factors in maintaining business continuity. By prioritizing the protection of data and ensuring that systems are quickly restored to operational status, a disaster recovery plan serves as a safety net that allows organizations to quickly return to normal functioning, thus ensuring that services remain available to users and minimizing the impact on business operations.

While the other options may be relevant in various contexts, they do not encompass the primary objective of disaster recovery in the same way. For example, improving network speeds, managing telecom services, or reducing operational costs might be secondary outcomes or considerations, but they do not fundamentally address the immediate need to safeguard critical data and maintain uptime during and after a disaster scenario.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy